Toronto, Ontario — King Street West is about to change for the better part of a year. The City of Toronto and the TTC will begin major infrastructure improvements on sections of King Street West on Monday, November 23, 2026, continuing through 2027, the City announced in a news release on Friday, November 20, 2026.
The work starts with the replacement of two 139-year-old watermains between Dufferin Street and Close Avenue, followed by joint City-TTC streetcar track renewal on the same stretch. Watermain work hours are generally 7 a.m. to 7 p.m., Monday to Friday. That first phase runs from November 23, 2026 to August 2027. Later phases follow at Spadina Avenue to Portland Street (as early as December 2026 to summer 2027), Bathurst Street to Shaw Street (spring 2027 to late 2027), the King Street West and York Street intersection (summer 2027), and Charlotte Street to University Avenue (fall to winter 2027).
For riders, the change that lands Monday is the diversion. Beginning November 23, 504/304 King streetcars will divert via Queen Street West between Shaw Street and Roncesvalles Avenue. As early as December, the diversion extends further east via Queen Street West between Spadina Avenue and Roncesvalles Avenue to accommodate the Spadina-to-Portland work.
Some changes are already in place. Since November 1, 504 King streetcars have been consolidated into a single branch operating between Dundas West Station and Broadview Station, 504C/304C King replacement buses have been running between Roncesvalles Avenue and the Distillery, 503 Kingston Road replacement buses have been extended west to Dufferin Gate Loop, and 508 Lake Shore streetcars have been temporarily suspended. Wheel-Trans service continues throughout construction.
To keep the extra Queen Street West streetcars moving, the City is adding temporary transit priority measures — extended no-stopping prohibitions and new left-turn restrictions between Roncesvalles Avenue and Spadina Avenue — and crews began installing that signage as early as November 18. On King Street West itself, watermain work will generally maintain one lane of traffic in each direction between Dufferin Street and Close Avenue and between Spadina Avenue and Portland Street, though intermittent intersection closures may be required and some intersecting streets may be converted to two-way traffic. Access to businesses and properties, and accessible pedestrian routes, will be maintained.
The project is part of a multi-year City-TTC infrastructure renewal program that began in 2020, coordinating watermain replacement and track renewal so the corridor is not dug up twice. Construction schedules are subject to change due to weather, site conditions and operational requirements, and the City and TTC say updates will continue throughout the project.
Why it matters: King is one of the busiest streetcar corridors in the country, and its watermains date to the 1880s. From Monday, every King rider west of Shaw is on a Queen Street diversion, and every driver on King West is down to one lane each way — a pattern that will move east in phases through 2027.